June 5, 2020: Raber Road Sewer Lines

241CorridorImprovementLogo

Week of June 8:

Main sewer lines are scheduled to be installed along the north side of Raber Road. This work is anticipated to take approximately two weeks. Traffic will be maintained with lane restrictions. Expect delays along Raber Road westbound approac...

Read on...

Massillon Road North Updates
Posted on: May 26, 2020

May 21, 2020: Construction set to begin week of May 26

Karvo Construction will officially begin construction the week of May 26, weather permitting. The initial work for the next month or two will be centered around Raber Road and continue up to Stein Road, and will include setting up work zones, bringing in ...

Read on...

Massillon Road North Updates
Posted on: May 15, 2020

May 15, 2020: Utility Relocation Continues as Construction Start Approaches

This week and into next the following utility work continues:

  • Dominion Energy has been onsite for the last couple of months relocating the existing gas line and installing new service lines throughout the corridor.  Gas lines and service lines nee...
Read on...

Massillon Road North Updates
Posted on: May 15, 2020

February 24, 2020 Dominion Energy Gas Line Relocation

Dominion Energy Utility Relocation Beginning Week of February 17

Dominion Energy will begin gas line relocation along the east side of Massillon Road from Raber to SR619 the week of February 17.

  • Installing new gas line and new service lines to all establish...
Read on...

Massillon Road North Updates
Posted on: May 15, 2020

Week of January 27, 2020

Tree Removal Scheduled for Monday, January 27, Weather Permitting

On Monday, January 27, expect delays as crews clear trees on the east side of Massillon Road (from Handel’s to Stein Road) on Monday, January 27. Work will begin at 8 a.m. and end ...

Read on...

Massillon Road North Updates
Posted on: May 15, 2020

Week of December 9-13, 2019

The City sent letters to businesses in the immediate construction area (those along Massillon Road North of I-77 to just past SR619) alerting them of our construction manager and inquiring for updated contact information.

Read on...

Massillon Road North Updates
Posted on: May 15, 2020

Week of Dec. 12, 2019

The Massillon Road North project will begin in late spring 2020; however, utility relocation has begun and will continue throughout the winter months leading up to the start of construction. 

  • This week December 2-6, 2019 -- AT&T is relocating ...
Read on...

Massillon Road North Updates