Massillon Road North Construction Updates

Welcome to the Massillon Road North Project blog.  For those interested in keeping tabs on the project and its monthly and weekly progress, please follow this blog.  

View All Posts

Feb 25

February 24, 2020 Dominion Energy Gas Line Relocation

Posted on February 25, 2020 at 10:46 AM by Valerie Wolford

Dominion Energy Utility Relocation Beginning Week of February 17

Dominion Energy will begin gas line relocation along the east side of Massillon Road from Raber to SR619 the week of February 17.
  • Installing new gas line and new service lines to all establishments in the corridor. When service transfers are ready to be completed, Dominion will notify those impacted prior to transfer.
  • A Dominion Energy inspector will be on-site throughout the utility relocation. 
  • Work is anticipated to take 6-8 weeks to complete, weather depending
  • Traffic will be maintained. Flaggers will be directing traffic when necessary.