Massillon Road North Construction Updates

Welcome to the Massillon Road North Project blog.  For those interested in keeping tabs on the project and its monthly and weekly progress, please follow this blog.  The Massillon Road North project will begin in late spring 2020; however, utility relocation has begun and will continue throughout the winter months leading up to the start of construction.
  • This week December 2-6, 2019 -- AT&T is relocating utilities across Massillon Road just south of SR619. The contractor will be working daily from 9 a.m. to 3:30 p.m. in the road-right-of-way and reducing traffic to one lane at times. Flaggers will be directing traffic. Please anticipate delays.
  • In addition, trees will be cleared from the right-of-way in December 2019/January 2020. Once we have confirmation of specific weeks for tree removal, we will share.
  • The City has engaged our Project Manager H.R. Gray. Project managers from H.R. Gray will be meeting with businesses along the project beginning the week of December 2 to introduce themselves and collect contact info, so our team can keep those in the immediate construction area informed throughout the project. 
  • To ensure you receive updates regarding the project, sign up for our text message alerts (also signs you up for emergency alerts as well. Please make sure you sign-up both your home address and work address (if you live and work in Green). If you work in Green, but live outside of the City, please use your work address to receive updates about Green. Signup for text alerts.

Dec 13

[ARCHIVED] Week of December 9-13

The original item was published from December 13, 2019 8:10 AM to December 13, 2019 8:10 AM

The City sent letters to businesses in the immediate construction area (those along Massillon Road North of I-77 to just past SR619) alerting them of our construction manager and inquiring for updated contact information.